- Intersection of Greenview Dr and Clubhouse Blvd
- New ADA compliant ramps;
- Resurface/re-stripe intersection;
- Resurface eastbound Clubhouse blvd. approach
- Phair Place
- Replace broken or separated sidewalk and curb-and-gutter;
- New ped crossing on north side of intersection of Phair and 10th;
- Resurface Phair Place
- 10th Street, from MD 198 to West Street
- Replace 3' sidewalk on east side of street;
- Replace broken or separated sidewalk and curb-and-gutter;
- New sidewalk and curb-and-gutter to replace existing drainage swale on west side between Phair Place and West Street;
- Resurface 10th Street
Tuesday, June 29, 2010
FY2011 Capital Improvement Projects Beginning
The City of Laurel has begun their FY 2011 "Street Improvements" CIP. These projects currently underway include: